ADNOC awards contract to expand capacity of its Shah Sour Gas Plant

Industry

The Abu Dhabi National Oil Company (ADNOC) has announced the award of a US$510mn engineering, procurement and construction (EPC) contract to expand the capacity of its Shah Sour Gas Plant

The investment supports ADNOC’s objective of enabling gas self-sufficiency for the UAE and underpins growth in gas production, in line with ADNOC’s 2030 strategy.

The EPC contract for the Optimum Shah Gas Expansion (OSGE) project was awarded by ADNOC Sour Gas (ASG) – a subsidiary of ADNOC – to Italy’s Saipem after a competitive tender process.  Over 50% of the award value will flow back into the UAE’s economy under ADNOC’s in-country value (ICV) programme, reinforcing ADNOC’s commitment to ensuring more economic value remains in the country from the contracts it awards.

The OSGE project is expected to be completed in 2023 and will increase the processing capacity of the Shah Gas Plant by 13%, from 1.28 to 1.45 billion standard cubic feet per day (SCFD). Shah, located 210 kilometers southwest of Abu Dhabi city, came on stream in 2015 and the OSGE project represents a cumulative expansion to 145% of the plant’s original capacity. 

Yaser Saeed Almazrouei, ADNOC upstream executive director, said, “The Shah Gas expansion project is an excellent example of how ADNOC is growing its gas production at existing fields to deliver a more sustainable gas supply and support the UAE’s gas self-sufficiency objective. Importantly, the in-country value generated from the EPC contract award will help to stimulate the growth of the private sector and local economy as we navigate the post-Covid recovery and continue to meet the future energy needs of our nation.”

Tayba Al Hashemi, CEO of ASG, added, “Shah’s expansion will optimise the plant as well as improve both capacity and higher-end product recoveries, further growing our contribution as a safe and reliable supplier of gas to ADNOC and the UAE. It enhances Shah’s position as a hub of sour operations expertise, developing the skills and experience of the next generation of Emirati professionals. Saipem was awarded this contract following a rigorous, competitive tender process.”

The scope of the OSGE project includes all associated off-sites and utilities necessary to integrate the new facilities with existing installations, including gas gathering facilities, main gas plant, product pipelines, and the sulfur granulation plant. The plant modifications have been designed for seamless integration with existing facilities with no impact on the safety or integrity of the plant while minimising impacts on production during construction, interfacing and commissioning.